Timescales and locations
The multi-storey improvement programme is expected to take around ten years to complete and the work for each block will be split into two phases:
- Phase 1, design and development - surveys, plans and designs for the block
- Phase 2, construction work - improvement works begin on site.
Phase 1 - design and development
2023 - 2025
2025 - 2027
- Leith - Cables Wynd House and Linksview House
- Moredun - Little France House,Marytree House, Moncrieffe House, Forteviot House, Casleview House and Moredun House
2027 - 2029
- Leith - Citadel Court, Kirkgate House and Persevere Court
- Pilton - Inchcolm Court and Inchgarvie Court
2029 - 2031
- Calders - Cobbinshaw House, Medwin House and Dunsyre House
- Hailesland - Drover's Bank, Midcairn and Kilncroft
2031 - 2033
- Pilton - Northview Court (tbc)
- Restalrig - Hawkhill Court and Nisbet Court (tbc)
Phase 2 - construction work
2023 - 2025
- Muirhouse - May Court and Gunnet Court
2025 - 2027
2027 - 2029
- Leith - Cables Wynd House and Linksview House
- Moredun - Little France House,Marytree House, Moncrieffe House, Forteviot House, Casleview House and Moredun House
2029 - 2031
- Leith - Citadel Court, Kirkgate House and Persevere Court
- Pilton - Inchcolm Court and Inchgarvie Court
2031 - 2033
- Calders - Cobbinshaw House, Medwin House and Dunsyre House
- Hailesland - Drover's Bank, Midcairn and Kilncroft
2033 - 2035
- Pilton - Northview Court (tbc)
- Restalrig - Hawkhill Court and Nisbet Court (tbc)